12/3/24 – DREDGING COMPLETED AT WAILOA SMALL BOAT HARBOR
Posted on Dec 3, 2024 in Boating & Ocean Recreations, Main, News Releases, slider
JOSH GREEN, M.D. GOVERNOR |
DAWN CHANG |
DREDGING COMPLETED AT WAILOA SMALL BOAT HARBOR
HILO, Hawai‘i – The long-awaited completion of the dredging work at Wailoa Small Boat Harbor in Hilo has finally come for Hawaiʻi Island boaters.
The dredging contractor wrapped up its operations on November 27 and will be removing its barge from Wailoa Small Boat Harbor on Saturday, December 7. The barge has occupied the harbor to facilitate dredging operations since the project started in July, and its removal is the final step to close out the project.
The final project cost increased from the initial budgeted amount of $3.1 million to $4.8 million, and the Division of Boating and Ocean Recreation (DOBOR), which manages Wailoa Small Boat Harbor, was able to cover the cost overrun with its Boating Special Fund, which derives its revenue from statewide harbor and boating facility use fees.
“We appreciate the public’s patience, understanding, and advocacy as DOBOR navigated the permitting and funding hurdles to get this project completed before the end of the year,” said Meghan Statts, DOBOR administrator. ”We also appreciate the legislature for recognizing the importance of this project and providing funding.”
# # #
RESOURCES
(All images/video courtesy: DLNR)
HD video – Wailoa Small Boat Harbor dredging (July 9, 2024):
HD video – Wailoa Small Boat Harbor dredging SOTS (July 9, 2024):
Photographs – Wailoa Small Boat Harbor dredging (July and Nov. 2024):
Media Contacts:
Ryan Aguilar
Communications Specialist
Hawaiʻi Dept. of Land and Natural Resources
Communications Office: 808-587-0396
Email: [email protected]