Image and video: Heavy construction equipment workers are ploughing away, reconfiguring the mountainside so it’s safe for traffic after a major landslide decimated the highway earlier in June. | Courtesy Wyoming Department of Transportation
JACKSON — Crews from Wyoming Department of Transportation (WYDOT) and Evans Construction are making significant progress on an ambitious plan to reconnect two lanes of Wyoming State Highway 22 following the massive Teton Pass landslide on June 8.
Workers have been packing dirt around the clock in an effort to safely and efficiently build a new interim road and reconnect one of the region’s most-used mountain thoroughfares.
According to the Wyoming Department of Transportation, its “geologists and engineers are confident they can build a safe, temporary detour around the slide area using local fill material and paving two temporary lanes. They are hoping to have a temporary detour open to the public, likely with some strict weight and width restrictions, in a few weeks.”
RELATED | Everything you need to know about the Teton Pass closure
“I want to express my gratitude to WYDOT Director Westby and his entire team for their efforts to rapidly develop and implement a plan to get traffic moving over Teton Pass again as quickly as possible,” Wyoming Governor Mark Gordon said in a WYDOT Facebook post last week.
RELATED | Teton Pass Road has ‘catastrophically failed’
Gordon issued an emergency declaration following the disaster that allowed the state to tap into Federal Highway Administration resources in order to fund the project.
Crews are also constructing a box culvert at milepost 15 where a a major mudslide occurred on June 7 to provide additional drainage.
RELATED | Teton Pass closed for second time in two days after mudslide
Plans to fully rebuild the road at milepost 12.8 for the long-term are still being developed, and officials have not issued a timeline for that phase of the project.
“WYDOT will be flying the area with a survey plane and doing some geological drilling in preparation for the reconstruction,” the department posted.
“WYDOT’s response through this crisis demonstrates the commitment, passion and ingenuity of our crews,” said WYDOT Director Darin Westby on Facebook. “We certainly want to thank the Governor, the Federal Highway Administration, the Idaho Transportation Department, the Wyoming Office of Homeland Security, Evans Construction and the US Forest Service for their quick response, teamwork and dependability in our time of need.”
This before and after drone footage shows the curve of Wyoming State Highway 22 at mile marker 12.8 in 2023 and again after the slide. | Courtesy Wyoming Department of Transportation
=htmlentities(get_the_title())?>%0D%0A%0D%0A=get_permalink()?>%0D%0A%0D%0A=htmlentities(‘For more stories like this one, be sure to visit https://www.eastidahonews.com/ for all of the latest news, community events and more.’)?>&subject=Check%20out%20this%20story%20from%20EastIdahoNews” class=”fa-stack jDialog”>